Cherry Substation

Substation Permitting
August 2004 - October 2004

Line Route Survey
August 2005 - November 2005

Line Engineering/Design
October 2005 - December 2008

Acquire Line Easements
November 2005 - June 2008

Line Construction
January - August 2009

Substation Construction
May - August 2009

Facilities In Service
September 2009