The proposed schedule for the Cambridge-McCall-Lake Fork 138-kV transmission line is as follows:
Transmission Line Route Study
March 2002 – November 2002
Environmental Studies
November 2002 – December 2006
Permitting and Approvals
January 2003 – December 2006
Cambridge to Council Segment
Right of Way Acquisition 2003 – 2005
Construction: November 2005 – November 2006
Council to McCall Segment
Right of Way Acquisition January 2004 – Ongoing
Construction planned for 2007
McCall to Lake Fork Segment
Right of Way Acquisition August 2005 – Ongoing
Construction planned for June – August 2007