Beacon Light Substation

Site Selection
October 2002 – December 2002

Conditional Use Permit
March 2005 – August 2005

Construction
When load dictates need.

In Service
Estimated 2012

Project Schedule - 138-kV Sub-transmission Line

Permitting
March 2005 – August 2005

Acquire Right-of-Way
August 2005 – December 2005

Construction
When load dictates need.

In Service
Estimated 2012