Beacon Light Substation
Site Selection
October 2002 – December 2002
Conditional Use Permit
March 2005 – August 2005
Construction
When load dictates need.
In Service
Estimated 2012
Project Schedule - 138-kV Sub-transmission Line
Permitting
March 2005 – August 2005
Acquire Right-of-Way
August 2005 – December 2005
Construction
When load dictates need.