The proposed schedule for the Gateway West Transmission Project follows.
National Environmental Policy Act ( NEPA) Process
2007-2009
Western Electric Coordinating Council (WECC) Rating Process
2007 – 2009
Bureau of Land Management (BLM) Right of Way Grants
2009 – 2011
Right of Way Acquisition
2007 – 2010
Permitting
2008 – 2011
Engineering
2008 – 2012
Construction
2012 – 2014
In Service
2012 – 2014