Cherry Substation
Project Need
According to U.S. Census figures, Canyon County was one of the fastest growing areas in the nation with a population jump of more than 15 percent between 2000 and 2003. During that same period, Idaho Power connected on average more than 2,700 new customers per year in the Canyon County area. This growth has substantially increased Idaho Power’s electrical load and is straining existing electric facilities.
To meet the power needs of some of this growth, Idaho Power plans to construct the Cherry Substation and associated 138,000-volt (138-kV) sub-transmission line. These facilities, planned to be in service in September 2009, will allow Idaho Power to continue providing reliable electric service to meet both existing and future electrical capacity needs for northeast Nampa.
Cherry Substation Details
The proposed Cherry Substation will be located on the southeast corner of Cherry Lane and Can-Ada Road. The substation will sit back off the road surrounded by a slatted chain link fence and landscaping. Click for a printable map .
The substation is used to transform electricity from 138kV to 12.5kV. Initially, three 12.5-kV distribution circuits will bring electricity from the substation to homes and businesses in the area. As the northeast Nampa area continues to grow, up to five additional 12.5-kV distribution circuits could be installed.
Typical proposed structure for Cherry Substation's source of power
Sub-Transmission Line Details
The exisiting 69-kV sub-transmission line portion, which runs through the golf course and then along the north side of Franklin Road, will be converted to 138kV. We will tap this line at the corner of Franklin Road and Can-Ada Road and construct a new 138-kV line which will run north along Can-Ada about one mile to Cherry Substation.
Most of the poles will be designed with the 138-kV sub-transmission circuit in the top position, and a 12.5-kV distribution circuit in the lower position. Road right of way or private easements will be used for the line corridor.
General Sub-transmission Structure Information
- Structure type: Tubular steel poles
- Structure color: Hazelton gray
- Structure heights: 75 feet to 85 feet
- Structure spacing: 300 feet average
An example of how an Idaho Power substation appears in an urban setting.
Project Schedule
The proposed schedule for the Cherry Substation Project is as follows:
Substation Permitting
August 2004 – October 2004
Line Route Survey
August 2005 – November 2005
Line Engineering/Design
October 2005 – December 2008
Acquire Line Easements
November 2005 – June 2010
Line Construction
January – August 2011
Substation Construction
May – August 2011
Facilities In Service
September 2011
Contact Information
If you have questions about the Cherry Substation project or have information you wish to be considered, contact:
Tim Phillips, Project Manager
Idaho Power
P.O. Box 70
Boise, ID 83707
Phone: 208-388-2744
e-mail: tphillips@idahopower.com
Kristi Pardue, Facility Siting Coordinator
Idaho Power
P.O. Box 70
Boise, ID 83707
Phone: 208-388-2415
e-mail: kpardue@idahopower.com
Related Information
Treasure Valley Projects
Garden Valley Projects
Oregon Projects
Regional Projects
Generation Projects
Twin Falls Area Projects
Wood River Valley Projects
© 1995-2010 Idaho Power Company.