Project Need

Southwest Ada County continues to see steady residential development and Idaho Power is working hard to keep up! In order to serve the growing electrical needs of the community, we anticipate that a new distribution substation will be required in the area of Ten Mile and Amity roads by May 2014. If growth increases beyond projections, this substation may be needed even sooner.

Idaho Power would like to establish a distribution substation site well in advance of construction. This makes the public aware of the location and positions us to best serve the power requirements of the area.

So far, Idaho Power has obtained a conditional use permit and purchased the land.

Typical proposed structure for Amity substation's source of power

Substation Details

The proposed Amity Substation is located on Amity Road, about 300 yards west of Ten Mile Road. View a printable map .

The substation will occupy less than 200 feet of road frontage and will set 100 feet back from the existing road right-of-way. A seven-foot tall, slatted chain link fence and landscaping will surround the substation.

The distribution substation will transform electricity from 138,000 volts to 12,500 volts (138 kV to 12.5 kV), and will initially be constructed to provide three 12.5-kV distribution circuits to bring electricity from the distribution substation to homes in the area. As the area continues to grow, up to five additional 12.5-kV distribution circuits could be provided by this station. The source of power for this substation will be a 138-kV sub-transmission line. The line route has not yet been determined, but it will likely come from the west, along Amity Road.

 

Idaho Power has posted signs at the site announcing the future construction of the substation. Until then the two-acre site will be leased back to the previous owner as pasture.

An example of how an Idaho Power substation appears in a rural setting.

Project Schedule

Substation Permitting

January 2005 – May 2005

Install Substation Sign

June 2005

Substation Design

August 2013 – November 2013

Substation Construction

January 2014 – May 2014

In Service

May 2014

Contact Information

If you have questions about the Amity Substation project or have information you wish to be considered, contact:

Keith Georgeson, Project Manager
Idaho Power
P.O. Box 70
Boise, ID 83707
Phone: 208-388-2034
e-mail: kgeorgeson@idahopower.com

Kristi Pardue, Facility Siting Coordinator
Idaho Power
P.O. Box 70
Boise, ID 83707
Phone: 208-388-2415
e-mail: kpardue@idahopower.com

Related Information

Garden Valley Projects

Oregon Projects

Generation Projects

Twin Falls Area Projects

Wood River Valley Projects

 

Server: mor
Port: 80
Secure: 0
session: 8430f62cd7f7194121fc451f58561a576b7a
sitearea: 0
Idaho Power Account Manager

Loading Account Information