Account Manager Login

Account Manager is in maintenance mode Account Manager

Account Manager is not available. Please check back again. We apologize for any inconvenience. Thank you for your patience!

Generator Interconnection Information

Generators and potential generators who wish to connect to Idaho Power's electrical system will find the following information and links helpful. Applications are placed in the queue and are processed on a first come, first serve basis. View the application list. This link will take you to the OASIS site. From the left menu bar, click "Generation Interconnection" and then "Generation Interconnection Queue."

View related documents:

 

Idaho Net Metering (less than 100KW)


Idaho Net Metering (less than 100KW)

Use the links below to learn about generating power from solar, wind or another renewable energy source at your home or business.

Oregon Generators up to 10MW


Oregon Generators up to 10MW

Use the links below to learn about generating power from solar, wind or another renewable energy source at your home or business.

Oregon Customers: Idaho Power is in the process of establishing the Oregon Solar Photovoltaic Pilot Program to demonstrate the use and effectiveness of volumetric incentive rates (VIRs) and payments for electricity delivered by solar photovoltaic energy (SPV) systems.

Oregon Generators over 20MW


Oregon Generators over 20MW

Use the links below to learn about generating power from solar, wind or another renewable energy source at your home or business.

Idaho Generators up to 20 MW


Idaho Process for Generators up to 20 MW


Small Generator Interconnection Procedures

Step 1:
The Interconnection Application must be completed and submitted for all Generator Interconnections to the Idaho Power System. Proof of Site Control and $1000 deposit is required.

Step 2:
Feasibility Analysis includes general review of system impact, capacity constraints and possible problems with the customer's choice of point of interconnection.

Step 3:
System Impact Study provides a detailed assessment of the transmission system adequacy to accommodate the application. This step may not be necessary for some projects depending on size and location of the project. A $10,000 deposit is required.

Step 4:
Facility Study includes design and engineering studies to determine the design and specifications. Construction options are provided to the customer. A deposit up to $30,000 is required.

Step 5:
Interconnection Agreement. all projects up to 20 MW are subject to technical requirements under the Interconnection Agreement once the project becomes operational.


Idaho Generators greater than 20 MW


Idaho Process for Generators greater than 20 MW


Large Generator Interconnection Procedures

Step 1:
The Large Generator Interconnection Application must be completed and submitted for all Generator Interconnections greater than 20 MW into the Idaho Power System. Proof of Site Control and $10,000 deposit is required.

Step 2:
Large Generator Feasibility Analysis includes general review of system impact, capacity constraints and possible problems with the customer's choice of point of interconnection.

Step 3:
Large Generator System Impact Study provides a detailed assessment of the transmission system adequacy to accommodate the application. A $50,000 deposit is required.

Step 4:
Large Generator Facility Study includes design and engineering studies to determine the design and specifications. Construction options are provided to the customer. A $100,000 deposit is required.

Step 5:
Large Generator Interconnection Agreement . All projects greater than 20 MW are subject to technical requirements under the Interconnection Agreement once the project becomes operational.

Qualified Reporting Entity Service for Renewable Energy Certificates


Qualified Reporting Entity Service for Renewable Energy Certificates


Idaho Power Company provides a Qualified Reporting Entity (QRE) service which is an independent, renewable energy tracking system for reporting meter information to the Western Renewable Energy Generation Information System (WREGIS). The tracking system was developed by the Western Electricity Coordinating Council (WECC) which covers the western region of the United States. Many parties in the WECC including Idaho Power are making use of this system to facilitate the creation and accounting for Renewable Energy Certificates (REC) activity.

A key element of WREGIS is the creation of each REC. By definition one megawatt-hour (MWH) from a Qualifying Renewable Energy generation facility creates one REC. Therefore it is critical that the WREGIS system be populated with accurate MWH generation data for each Qualifying Renewable Energy generation facility.

Idaho Power as a Balancing Authority is a logical source for this accurate MWH data as it is the same MWH metering data that is required to perform our Balancing Authority duties. The Qualified Reporting Entity (QRE) service is not a mandated service required by regulation. Idaho Power and various other stake holders have developed a VOLUNTARY AGREEMENT to contract with Idaho Power for this QRE service.

 

Primary Contacts

Generator Interconnection - Physical Connection to the Wires
Josh Harris
208-388-2658 (voice)
208-388-5504 (fax)
jharris@idahopower.com

Net Meter Applications and Renewable Energy Questions
Scott Gates
208-388-2518 (voice)
208-388-6910 (fax)
sgates@idahopower.com

QRE Service Questions
Aubrae Sloan
208-388-5697 (voice)
208-388-6911 (fax)
asloan@idahopower.com

Please Note

Generators will be subject to certain obligations under different agreements such as Power Sales, Generator Interconnection and Transmission Service. Each generator is unique depending on size or location of the project and energy disposition for determining whether jurisdiction is under the Idaho or Oregon Public Utilities Commission (IPUC or OPUC), or the Federal Energy Regulatory Commission (FERC).

 

Server: mor