Account Manager Login

Generator Interconnection Information

Generators and potential generators who wish to connect to Idaho Power's electrical system will find the following information and links helpful. Applications are placed in the queue and are processed on a first come, first serve basis. View the application list. This link will take you to the OASIS site. From the left menu bar, click "Generation Interconnection" and then "Generation Interconnection Queue."

View related documents:

 

Net Metering (less than 100KW)


Net Metering (less than 100KW)

Use the links below to learn about generating power from solar, wind or another renewable energy source at your home or business.

Generators up to 20 MW


Process for Generators up to 20 MW


Small Generator Interconnection Procedures

Step 1:
The Interconnection Application must be completed and submitted for all Generator Interconnections to the Idaho Power System.

Step 2:
Feasibility Analysis includes general review of system impact, capacity constraints and possible problems with the customer's choice of point of interconnection.

Step 3:
System Impact Study provides a detailed assessment of the transmission system adequacy to accommodate the application. This step may not be necessary for some projects depending on size and location of the project.

Step 4:
Facility Study includes design and engineering studies to determine the design and specifications. Construction options are provided to the customer.

Step 5:
Interconnection Agreement. all projects up to 20 MW are subject to technical requirements under the Interconnection Agreement once the project becomes operational.


Generators greater than 20 MW


Process for Generators greater than 20 MW


Large Generator Interconnection Procedures

Step 1:
The Large Generator Interconnection Application must be completed and submitted for all Generator Interconnections greater than 20 MW into the Idaho Power System.

Step 2:
Large Generator Feasibility Analysis includes general review of system impact, capacity constraints and possible problems with the customer's choice of point of interconnection.

Step 3:
Large Generator System Impact Study provides a detailed assessment of the transmission system adequacy to accommodate the application.

Step 4:
Large Generator Facility Study includes design and engineering studies to determine the design and specifications. Construction options are provided to the customer.

Step 5:
Large Generator Interconnection Agreement . All projects greater than 20 MW are subject to technical requirements under the Interconnection Agreement once the project becomes operational.

 

Primary Contacts

Generator Interconnection - Physical Connection to the Wires
Rowena Bishop
208-388-2658 (voice)
208-388-5504 (fax)
rbishop@idahopower.com

Net Meter Applications
Candace Gentry
208-388-2276 (voice)
208-388-6647 (fax)
cgentry@idahopower.com

Renewable Energy Questions
Scott Gates
208-388-2518 (voice)
208-388-6910 (fax)
sgates@idahopower.com

Please Note

Generators will be subject to certain obligations under different agreements such as Power Sales, Generator Interconnection and Transmission Service. Each generator is unique depending on size or location of the project and energy disposition for determining whether jurisdiction is under the Idaho or Oregon Public Utilities Commission (IPUC or OPUC), or the Federal Energy Regulatory Commission (FERC).

 

Server: kentonprod
Port: 80
Secure: 0
session: 3c30bb48990d1f3d446155454c75654a1f4e
sitearea: 0
Idaho Power Account Manager

Loading Account Information